Mackay Road A study has been completed on Mackay Road between Adams Farm Parkway and High Point Road on ways to improve vehicle and pedestrian safety and vehicle capacity. This project involves adding turn lanes, monolithic islands, and sidewalks for pedestrian safety. Options that were studied include:
- Widening to a five-lane section
- Adding sidewalks along both sides of Mackay Road
- Installing a four-foot concrete monolithic island to the High Point Road approach
- Adding dual left-turn lanes onto High Point Road and on Adams Farm Parkway onto Mackay Road
- Marking extra storage lengths for various turn lanes.
This project is currently under design and is scheduled to start construction in spring 2014.
Questions or comments?
|