South Elm-Eugene Street
Phase I - Vandalia Road to Vivian Lane
Existing: Two-lane ribbon pavement
Scope: Construct four-lane median section
Status: Construction complete

Phase II - JJ Drive to Vandalia Road
Existing: Five-lane curb and gutter section
Scope: Construct grass median within existing curb limits. Includes sidewalk construction on west side and intersection radius improvements at Creek Ridge/Industrial, JJ Drive, and Vandalia Road
Status: Feasibility study completed, engineering design complete, currently acquiring right-of-way.
Estimated Construction Start: Spring 2007