Intersection Improvements

These projects address congestion at some of Greensboro's busiest intersections. Additional public funding will be needed to finance construction during the next 10 years.

What do you think?
Please complete our Online Survey to provide feedback on transportation needs.

Cone Boulevard - Elm Street Intersection

Package A
ID Intersections Owner District

Estimated Cost

I-1 W. Market St and College Rd State 4 $6,890,000
I-2 Battleground Ave and Cone Blvd State / City 3 $4,600,000
I-3 Clifton Rd and Wendover Ave State 5 $540,000
I-4 NC 68 and Pleasant Ridge Rd State 4 $2,300,000
I-5 Lawndale Dr and Pisgah Church Rd City 3 $3,510,000
I-6 Elm St and Pisgah Church Rd City 3 $3,510,000

Subtotal =>

$21,350,000
Package B - Includes all projects in Package A and the projects shown below
ID Intersections Owner District

Estimated Cost

I-7 Bryan Blvd WB ramp and New Garden Rd State / City 4 $4,460,000
I-8 Air Harbor Rd and Lake Brandt Rd State / City 3 $1,310,000
I-9 Downtown Bulbouts City 1, 2 $450,000
I-10 Friendly Ave and Friendway Rd State / City 4 $230,000
I-11 Norwalk Ave and Wendover Ave State / City 5 $540,000
I-12 Florida St and Randolph Ave City 1 $510,000
I-13 Albert Pick Rd and NC 68 State 4 $450,000
I-14 Fleming Rd and Lewiston Rd State 4 $450,000
I-15 Fleming Rd and Pleasant Ridge Rd State 4 $450,000

Subtotal =>

$30,200,000
Package C - Includes all projects in Packages A and B and the projects shown below
ID Intersections Owner District

Estimated Cost

I-16 Green Valley Rd and Pembroke Rd / Westover Ter City 3 $1,760,000
I-17 Church St and Pisgah Church Rd and Lees Chapel Rd State / City 2, 3 $2,700,000
I-18 College Rd and New Garden Rd and Friendly Ave State / City 4 $2,700,000
I-19 Phillips Ave and Summit Ave State 2 $1,760,000
I-20 Holden Rd and Vandalia Rd City 5 $880,000

Subtotal => 

$40,000,000