Review this one-year forecast of future infrastructure contracts

Table one lists construction and remodeling contracts for City buildings/facilities (i.e. fire stations, libraries, parks, etc.) overseen by the Facilities Division of the Engineering and Inspections Department.

Table two lists construction contracts for City Infrastructure (i.e. roadways, sidewalks, water and sewer utilities, etc.) overseen by the department's Engineering Division.

Building Facilities

City Contracts

Contract

Project

Advertisement

Pre-Bid

Award Notice
TBD  NTB J. Douglas Galyon Depot Ticketing Renovation  February 27, 2020     
TBD  Asbestos Abatement  February 23, 2020     
2019-0590  Demolition of 2834 E. Market St.  February 23, 2020     
2019-0990  Demolition of 401 W. Avondale St.  February 10, 2020     
TBD  Glenwood Rec Parking Lot  January 30, 2020     
TBD  Battleground Parks District Phase 1  December 8, 2019     
2019-0890  Adaptive & Inclusive Offices at Sportsplex  November 21, 2019     
2019-0700  POD Break Room Renovation  November 21, 2019     

Infrastructure

Contracts Opportunities

Contract

Project

Advertisement

Pre-Bid

Award Notice

2016-066  Liberty Road Water and Sewer Improvements,
Phase 1 
March 12, 2020     
2020-001A  Street Resurfacing - Part 2  January 30, 2020  February 23, 2020   
2017-071  Forest Oaks Loop Feed Water Line Extension  January 16, 2020  January 30, 2020   
2014-053  Latham Park Greenway EB-5518  January 9, 2020  January 23, 2020   
2018-046A  Groometown Road Water Booster Station  February 27, 2020     
2017-093  Hilltop Road Lift Station, Force Main, Gravity Sewer Improvements  October 10, 2019  October 24, 2019  February 25, 2020 
2017-086  Sandy Ridge Road Sewer Outfall Construction  September 26, 2019  October 10, 2019  January 24, 2020 
2017-039A  Townsend Water Treatment Plant Lagoon 2  September 19, 2019  October 3, 2019  January 28, 2020 
2013-090  Pisgah/Lees Chapel/Yanceyville Sidewalks Part C&D  August 1, 2019  August 15, 2019  November 15, 2019 
2019-048  Water Valve Replacement - Phase 1  November 5, 2019 November 12, 2019  January 24, 2020