Cotswold & Old Battleground

Print
Press Enter to show all options, press Tab go to next option

Project Overview 

On December 7, 2017 the Greensboro Department of Transportation (GDOT) hosted a public workshop at the Lewis Recreation Center, with an online comment opportunity that continued through January 5, 2018. The purpose was to provide information and to get public input on design alternatives for the Old Battleground Road and Cotswold Terrace intersection.

On March 1 and 19, 2018, GDOT hosted meetings on the Selected Design Alternative at the Lewis Recreation Center. The combined attendance of these meetings was 113 people. The purpose was to provide information, get public input on this decision, and address concerns and thoughts that people had on the Selected Design Alternative. An online comment opportunity ran from March 1 through April 9, 2018.

Current Project Schedule

  • Design Completion: Fall 2018
  • Bid Opening: February 2019
  • Contract Award: March 2019
  • Construction Start: May 2019
  • Number of Days to Complete: 180