Project Update

Construction Plans are being finalized for the Greene Street streetscape and two-way conversion project. A public meeting will be held at January 31, at Collab, 229 N. Greene St. Drop in anytime between 11 am and 1 pm or 4-6 pm. Residents can view drawings and share input.  

Two-way conversion recommendations:

  • two lanes southbound
  • one lane northbound
  • Traffic signal modifications
  • parking deck modifications

Streetscape Features:

  • Sidewalk bulbouts at intersections
  • Decorative crosswalks
  • New sidewalk and curb & gutter
  • Sidewalk bulbouts with tree wells

Anticipated Schedule

  • Complete Construction Drawings - Spring 2019
  • Begin Utility Relocation - Spring 2019
  • Begin Construction - Winter 2019/2020
  • End Construction - Fall 2020