Project History

East Vandalia Road between South Elm-Eugene Street to Pleasant Garden Road is planned for improvements to increase vehicle capacity and enhance safety for drivers, pedestrians, and cyclists. Design is on-going but nearing completion. A portion of the project was redesigned to comply with updated federal guidelines.

Recommended improvements include:

  • Widening to three lanes with a center turn lane. 
  • Installing bike lanes.
  • Installing curb and gutter.  
  • Installing sidewalks. 
  • See Design Plans.

Anticipated Schedule

  • Complete culvert design – Fall 2025
  • Submit plans for NCDOT Review – Winter 2025
  •  Complete Right-of-Way Acquisition / Begin utility relocation – Spring 2026
  • Advertise for construction – Spring 2027
  • Begin construction – Fall 2027
  • Complete construction – Spring 2029